Ship Project Status Report
(Blue Book)
Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM
S H I P H A B I T A B I L I T Y P R O J E C T D A T A
| WILLIAM P LAWRENCE (DDG 110) |
55686-261
ACTIVE PROJECT
|
CLASS: DDG 51 (Flight IIA Variant) |
HOMEPORT: PEARL |
PLANNING YARD: BATH |
|
| POC: Stephen Ferderer, CNSP N43 |
PHONE: 619-437-2757 |
|
| ENGINEERING WORK SCOPE |
| SURVEY AVAILABILITY: |
FY 21 DSRA1 |
| SURVEY DATES: |
03/01/2021 - 01/19/2022 |
| SURVEY LOCATION: |
PEARL |
| DESIGN AGENT: |
DELPHINUS |
|
| INSTALLATION WORK SCOPE |
| INSTALL AVAILABILITY: |
FY 26 SRA2-1
(319 days) |
| INSTALL DATES: |
11/10/2025 - 09/25/2026
|
| INSTALL LOCATION: |
PEARL |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
14 / 292 |
4 / 27 |
0 / 0 |
0 / 0 |
18 / 319 |
| SANITARY SPACE / FIXTURES: |
17 / 68 |
5 / 17 |
0 / 0 |
0 / 0 |
22 / 85 |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
3 / 45 |
0 / 0 |
0 / 0 |
0 / 0 |
3 / 45 |
| SANITARY SPACE / FIXTURES: |
4 / 13 |
0 / 0 |
0 / 0 |
0 / 0 |
4 / 13 |
|
| OTHER PROJECT: |
|
| PROJECT NO(S): |
BCPO-E9268, BENL-E9278, HCPO-E9279, HENL-E9280 |
| REMARKS: |
|
|
| OTHER PROJ: |
|
| REMARKS: |
CC # 4 & 6, WORK SCOPE REDUCED DUE TO TIME.
|
|
| HABITABILITY DRAWING NUMBERS |
| DISCIPLINE |
HAB DRAWING NUMBER |
NAVSEA DRAWING NUMBER |
| ARRANGEMENT-BERTHING |
22-DDG 110-01 A |
640 - 8866646 REV A |
| ARRANGEMENT-SANITARY |
22-DDG 110-03 A |
644 - 8866647 REV A |
| VENTILATION-BERTHING |
22-DDG 110-10 A |
512 - 8866648 REV A |
| VENTILATION-SANITARY |
22-DDG 110-12 A |
512 - 8866649 REV A |
| PIPE-SANITARY |
22-DDG 110-20 A |
505 - 8866650 REV A |
| ELECTRICAL-BERTHING |
22-DDG 110-30 A |
331 - 8866651 REV A |
| ELECTRICAL-SANITARY |
22-DDG 110-32 A |
331 - 8866652 REV A |
| MFG DETAILS DRAWINGS (52) IS NOT REQUIRED. |
|
| PROJECT NUMBERS(s) AND COMPARTMENTS |
BENL-S9278
3-300-1-L (27)
3-326-1-T (0)
3-338-3-L (18)
PT 3 (45)
HENL-S9280
3-325-1-L (6)
3-335-1-A (1)
3-338-5-A (1)
3-338-7-L (5)
PT 4 (13)
|
|
| MILESTONES |
SCHEDULED |
ACTUAL |
EVENTS |
| 01/11/2024 |
12/01/2021 |
12/01/2021
|
START SURVEY |
| 02/09/2024 |
12/12/2021 |
12/12/2021
|
COMPLETE SURVEY |
| 03/12/2024 |
01/12/2022 |
01/05/2022
|
SEND SURVEY REPORT TO PM |
| 01/30/2024 |
06/12/2024 |
06/17/2024
|
TC ISSUE ADVANCE PLANNING NOTICE TO SHIP |
| 02/29/2024 |
07/12/2024 |
09/26/2024
|
SHIP RESPOND TO ADVANCE PLANNING NOTICE |
| 09/16/2024 |
09/16/2024 |
10/11/2024
|
SO SUBMIT DRAWINGS TO PM & PY |
| 09/16/2024 |
09/16/2024 |
10/14/2024
|
SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM |
| 05/14/2025 |
05/14/2025 |
Pending
|
PROJECT MATERIAL PROCUREMENT FUNDED |
| 08/11/2025 |
08/11/2025 |
Pending
|
PROJECT INSTALLATION FUNDED |
| 11/10/2025 |
11/10/2025 |
11/10/2025
|
START AVAILABILITY |
| 11/10/2025 |
11/10/2025 |
11/10/2025
|
START PROJECT |
| 09/25/2026 |
09/25/2026 |
Pending
|
COMPLETE PROJECT |
| 09/25/2026 |
09/25/2026 |
Pending
|
COMPLETE AVAILABILITY |
| Project Record Last Updated: 06/03/2026 |
|