Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM

Select by Ship Name: 

Select by Ship Hull: 

 

WAYNE E MEYER (DDG 108)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
  FY 27 ISRA4-1   02/08/2027 - 07/07/2027 6 / 73 (b)   0 / 0 (f) 09/23/2020 Active
FY 31 DMP   05/26/2031 - 09/29/2033 12 / 246 (b)   22 / 85 (f) 02/11/2027 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
WAYNE E MEYER (DDG 108) 55684-272
ACTIVE PROJECT
CLASS: DDG 51
(Flight IIA Variant)
HOMEPORT: PEARL PLANNING YARD: BATH
POC: Stephen Ferderer, CNSP N43 PHONE: 619-437-2757
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 20 DSRA1
SURVEY DATES: 03/16/2020 - 01/29/2021
SURVEY LOCATION: PEARL
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 27 ISRA4-1     (149 days)
INSTALL DATES: 02/08/2027 - 07/07/2027
INSTALL LOCATION: PEARL
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 14 / 292 4 / 27 0 / 0 0 / 0 18 / 319
SANITARY SPACE / FIXTURES: 17 / 68 5 / 17 0 / 0 0 / 0 22 / 85
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 6 / 73 0 / 0 0 / 0 0 / 0 6 / 73
SANITARY SPACE / FIXTURES: 0 / 0 0 / 0 0 / 0 0 / 0 0 / 0
OTHER PROJECT:
PROJECT NO(S): BCPO-E8298, BENL-E8299, HCPO-E8302, HENL-E8303
REMARKS:
OTHER PROJ:
REMARKS: SKED CHG TO ISRA4-1 FY27 08FEB27-07JUL27 (150D). WORK SCOPE REDUCTION REQUIRED.
CREW BERTHING #3 ONLY DUE TO SHORTEN AVAIL.
SECOND APM SENT 12/22/25.

HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-BERTHING 20-DDG 108-01  B 640 - 8866564  REV B
VENTILATION-BERTHING 20-DDG 108-10  B 512 - 8866566  REV B
ELECTRICAL-BERTHING 20-DDG 108-30  B 331 - 8866569  REV B
VENTILATION-MFG DET 20-DDG 108-52  B 512 - 8866571  REV B
PROJECT NUMBERS(s) AND COMPARTMENTS
BENL-S8299
2-300-1-L (8)
2-300-3-L (23)
2-310-2-L (36)
2-314-3-L (0)
2-314-5-L (0)
2-326-1-L (6)
 PT 6 (73)
MILESTONES SCHEDULED ACTUAL EVENTS
04/10/2025 09/23/2020 09/23/2020 START SURVEY
05/09/2025 10/04/2020 10/04/2020 COMPLETE SURVEY
06/10/2025 11/04/2020 10/28/2020 SEND SURVEY REPORT TO PM
04/29/2025 04/29/2025 04/28/2025 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
05/29/2025 05/29/2025 07/22/2025 SHIP RESPOND TO ADVANCE PLANNING NOTICE
12/15/2025 12/15/2025 12/19/2025 SO SUBMIT DRAWINGS TO PM & PY
12/15/2025 12/15/2025 12/22/2025 SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
08/12/2026 08/12/2026 Pending PROJECT MATERIAL PROCUREMENT FUNDED
11/09/2026 11/09/2026 Pending PROJECT INSTALLATION FUNDED
02/08/2027 02/08/2027 Pending START AVAILABILITY
02/08/2027 02/08/2027 Pending START PROJECT
07/07/2027 07/07/2027 Pending COMPLETE PROJECT
07/07/2027 07/07/2027 Pending COMPLETE AVAILABILITY
Project Record Last Updated: 12/22/2025