RAFAEL PERALTA (DDG 115)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
  FY 28 DSRA1   03/20/2028 - 02/12/2029 6 / 84 (b)   8 / 25 (f) 11/20/2024 Active
FY 31 SRA2-1   06/09/2031 - 02/01/2032 2 / 135 (b)   4 / 26 (f) 03/20/2028 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
RAFAEL PERALTA (DDG 115) 50126-282
ACTIVE PROJECT
CLASS: DDG 51
(Flight IIA Variant)
HOMEPORT: YOKO PLANNING YARD: BATH
POC: Stephen Ferderer, CNSP N43 PHONE: 619-437-2757
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 24 SRA1-2
SURVEY DATES: 09/03/2024 - 04/15/2025
SURVEY LOCATION: SRFYOKO
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 28 DSRA1     (329 days)
INSTALL DATES: 03/20/2028 - 02/12/2029
INSTALL LOCATION: SRFYOKO
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 6 / 84 0 / 0 0 / 0 0 / 0 6 / 84
SANITARY SPACE / FIXTURES: 8 / 25 0 / 0 0 / 0 0 / 0 8 / 25
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 6 / 84 0 / 0 0 / 0 0 / 0 6 / 84
SANITARY SPACE / FIXTURES: 8 / 25 0 / 0 0 / 0 0 / 0 8 / 25
OTHER PROJECT:
PROJECT NO(S): BENL-E5364, HENL-E5430
REMARKS:
OTHER PROJ:
REMARKS:
HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-BERTHING 25-DDG 115-01  A 640 - 8937693  REV A
ARRANGEMENT-SANITARY 25-DDG 115-03  A 644 - 8937694  REV A
VENTILATION-BERTHING 25-DDG 115-10  A 512 - 8937695  REV A
VENTILATION-SANITARY 25-DDG 115-12  A 512 - 8937696  REV A
PIPE-SANITARY 25-DDG 115-20  A 505 - 8937697  REV A
ELECTRICAL-BERTHING 25-DDG 115-30  A 331 - 8937698  REV A
ELECTRICAL-SANITARY 25-DDG 115-32  A 331 - 8937699  REV A
VENTILATION-MFG DET 25-DDG 115-52  A 512 - 8937700  REV A
PROJECT NUMBERS(s) AND COMPARTMENTS
BENL-S5364
3-300-1-L (27)
3-310-2-L (21)
3-326-1-T (0)
3-338-3-L (18)
3-338-6-L (0)
3-350-2-L (18)
 PT 6 (84)
HENL-S5430
3-300-2-L (5)
3-306-2-A (1)
3-325-1-L (6)
3-335-1-A (1)
3-338-5-A (1)
3-338-7-L (5)
3-338-8-A (1)
3-338-10-L (5)
 PT 8 (25)
MILESTONES SCHEDULED ACTUAL EVENTS
05/21/2026 11/20/2024 11/20/2024 START SURVEY
06/19/2026 12/01/2024 12/01/2024 COMPLETE SURVEY
07/21/2026 01/02/2025 01/07/2025 SEND SURVEY REPORT TO PM
06/09/2026 06/09/2026 06/08/2026 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
07/09/2026 07/09/2026 Pending SHIP RESPOND TO ADVANCE PLANNING NOTICE
01/25/2027 01/25/2027 Pending SO SUBMIT DRAWINGS TO PM & PY
01/25/2027 01/25/2027 Pending SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
09/22/2027 09/22/2027 Pending PROJECT MATERIAL PROCUREMENT FUNDED
12/20/2027 12/20/2027 Pending PROJECT INSTALLATION FUNDED
03/20/2028 03/20/2028 Pending START AVAILABILITY
03/20/2028 03/20/2028 Pending START PROJECT
02/12/2029 02/12/2029 Pending COMPLETE PROJECT
02/12/2029 02/12/2029 Pending COMPLETE AVAILABILITY