Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM

Select by Ship Name: 

Select by Ship Hull: 

 

ANCHORAGE (LPD 23)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
  FY 27 SRA2-1   08/18/2027 - 09/20/2028 10 / 249 (b)   18 / 78 (f) 08/11/2023 Active
FY 31 SRA2-2   04/15/2031 - 01/19/2033 8 / 183 (b)   14 / 60 (f) 08/18/2027 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
ANCHORAGE (LPD 23) 3015A-274
ACTIVE PROJECT
CLASS: LPD 17
(FLIGHT 1)
HOMEPORT: SDGO PLANNING YARD: HII
POC: Stephen Ferderer, CNSP N43 PHONE: 619-437-2757
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 23 DSRA1
SURVEY DATES: 07/24/2023 - 06/09/2025
SURVEY LOCATION: SDGO
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 27 SRA2-1     (399 days)
INSTALL DATES: 08/18/2027 - 09/20/2028
INSTALL LOCATION: SDGO
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 12 / 330 8 / 34 0 / 0 0 / 0 20 / 364
SANITARY SPACE / FIXTURES: 21 / 88 8 / 15 0 / 0 0 / 0 29 / 103
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 10 / 249 0 / 0 0 / 0 0 / 0 10 / 249
SANITARY SPACE / FIXTURES: 18 / 78 0 / 0 0 / 0 0 / 0 18 / 78
OTHER PROJECT:
PROJECT NO(S): BCPO-E2313, BENL-E2367, HCPO-E2380, HENL-E2381
REMARKS:
OTHER PROJ:
REMARKS: LWMB WILL BE INSTALLED INSTEAD OF SITUP BERTHS.
WORK SCOPE HAS BEEN REDUCED DUE TO PROPOSED SHORTEN OF AVAIL.
HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-BERTHING 23-LPD 23-01  A 640 - 8866746  REV A
ARRANGEMENT-SANITARY 23-LPD 23-03  A 644 - 8866747  REV A
VENTILATION-BERTHING 23-LPD 23-10  A 512 - 8866748  REV A
VENTILATION-SANITARY 23-LPD 23-12  A 512 - 8866749  REV A
PIPE-SANITARY 23-LPD 23-20  A 505 - 8866750  REV A
ELECTRICAL-BERTHING 23-LPD 23-30  A 331 - 8866751  REV A
ELECTRICAL-SANITARY 23-LPD 23-32  A 331 - 8866752  REV A
VENTILATION-MFG DET 23-LPD 23-52  A 512 - 8866753  REV A
PROJECT NUMBERS(s) AND COMPARTMENTS
BENL-S2367
3-33-0-L (39)
3-33-2-L (27)
 PT 2 (66)
HENL-S2381
3-37-2-L (8)
3-37-3-L (8)
3-40-1-A (1)
3-40-3-A (1)
 PT 4 (18)
MILESTONES SCHEDULED ACTUAL EVENTS
10/17/2025 08/11/2023 08/11/2023 START SURVEY
11/17/2025 08/30/2023 08/30/2023 COMPLETE SURVEY
12/18/2025 09/27/2023 09/22/2023 SEND SURVEY REPORT TO PM
11/06/2025 11/06/2025 11/05/2025 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
12/05/2025 12/05/2025 02/17/2026 SHIP RESPOND TO ADVANCE PLANNING NOTICE
06/24/2026 06/24/2026 07/14/2026 SO SUBMIT DRAWINGS TO PM & PY
06/24/2026 06/24/2026 07/14/2026 SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
02/19/2027 02/19/2027 Pending PROJECT MATERIAL PROCUREMENT FUNDED
05/19/2027 05/19/2027 Pending PROJECT INSTALLATION FUNDED
08/18/2027 08/18/2027 Pending START AVAILABILITY
08/18/2027 08/18/2027 Pending START PROJECT
09/20/2028 09/20/2028 Pending COMPLETE PROJECT
09/20/2028 09/20/2028 Pending COMPLETE AVAILABILITY
Project Record Last Updated: 08/27/2026