Ship Project Status Report
(Blue Book)
Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM
S H I P H A B I T A B I L I T Y P R O J E C T D A T A
| ANCHORAGE (LPD 23) |
3015A-274
ACTIVE PROJECT
|
CLASS: LPD 17 (FLIGHT 1) |
HOMEPORT: SDGO |
PLANNING YARD: HII |
|
| POC: Stephen Ferderer, CNSP N43 |
PHONE: 619-437-2757 |
|
| ENGINEERING WORK SCOPE |
| SURVEY AVAILABILITY: |
FY 23 DSRA1 |
| SURVEY DATES: |
07/24/2023 - 06/09/2025 |
| SURVEY LOCATION: |
SDGO |
| DESIGN AGENT: |
DELPHINUS |
|
| INSTALLATION WORK SCOPE |
| INSTALL AVAILABILITY: |
FY 27 SRA2-1
(399 days) |
| INSTALL DATES: |
08/18/2027 - 09/20/2028
|
| INSTALL LOCATION: |
SDGO |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
12 / 330 |
8 / 34 |
0 / 0 |
0 / 0 |
20 / 364 |
| SANITARY SPACE / FIXTURES: |
21 / 88 |
8 / 15 |
0 / 0 |
0 / 0 |
29 / 103 |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
10 / 249 |
0 / 0 |
0 / 0 |
0 / 0 |
10 / 249 |
| SANITARY SPACE / FIXTURES: |
18 / 78 |
0 / 0 |
0 / 0 |
0 / 0 |
18 / 78 |
|
| OTHER PROJECT: |
|
| PROJECT NO(S): |
BCPO-E2313, BENL-E2367, HCPO-E2380, HENL-E2381 |
| REMARKS: |
|
|
| OTHER PROJ: |
|
| REMARKS: |
LWMB WILL BE INSTALLED INSTEAD OF SITUP BERTHS.
WORK SCOPE HAS BEEN REDUCED DUE TO PROPOSED SHORTEN OF AVAIL. |
|
| HABITABILITY DRAWING NUMBERS |
| DISCIPLINE |
HAB DRAWING NUMBER |
NAVSEA DRAWING NUMBER |
| ARRANGEMENT-BERTHING |
23-LPD 23-01 A |
640 - 8866746 REV A |
| ARRANGEMENT-SANITARY |
23-LPD 23-03 A |
644 - 8866747 REV A |
| VENTILATION-BERTHING |
23-LPD 23-10 A |
512 - 8866748 REV A |
| VENTILATION-SANITARY |
23-LPD 23-12 A |
512 - 8866749 REV A |
| PIPE-SANITARY |
23-LPD 23-20 A |
505 - 8866750 REV A |
| ELECTRICAL-BERTHING |
23-LPD 23-30 A |
331 - 8866751 REV A |
| ELECTRICAL-SANITARY |
23-LPD 23-32 A |
331 - 8866752 REV A |
| VENTILATION-MFG DET |
23-LPD 23-52 A |
512 - 8866753 REV A |
|
| PROJECT NUMBERS(s) AND COMPARTMENTS |
BENL-S2367
3-33-0-L (39)
3-33-2-L (27)
PT 2 (66)
HENL-S2381
3-37-2-L (8)
3-37-3-L (8)
3-40-1-A (1)
3-40-3-A (1)
PT 4 (18)
|
|
| MILESTONES |
SCHEDULED |
ACTUAL |
EVENTS |
| 10/17/2025 |
08/11/2023 |
08/11/2023
|
START SURVEY |
| 11/17/2025 |
08/30/2023 |
08/30/2023
|
COMPLETE SURVEY |
| 12/18/2025 |
09/27/2023 |
09/22/2023
|
SEND SURVEY REPORT TO PM |
| 11/06/2025 |
11/06/2025 |
11/05/2025
|
TC ISSUE ADVANCE PLANNING NOTICE TO SHIP |
| 12/05/2025 |
12/05/2025 |
02/17/2026
|
SHIP RESPOND TO ADVANCE PLANNING NOTICE |
| 06/24/2026 |
06/24/2026 |
07/14/2026
|
SO SUBMIT DRAWINGS TO PM & PY |
| 06/24/2026 |
06/24/2026 |
07/14/2026
|
SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM |
| 02/19/2027 |
02/19/2027 |
Pending
|
PROJECT MATERIAL PROCUREMENT FUNDED |
| 05/19/2027 |
05/19/2027 |
Pending
|
PROJECT INSTALLATION FUNDED |
| 08/18/2027 |
08/18/2027 |
Pending
|
START AVAILABILITY |
| 08/18/2027 |
08/18/2027 |
Pending
|
START PROJECT |
| 09/20/2028 |
09/20/2028 |
Pending
|
COMPLETE PROJECT |
| 09/20/2028 |
09/20/2028 |
Pending
|
COMPLETE AVAILABILITY |
| Project Record Last Updated: 08/27/2026 |
|