S H I P H A B I T A B I L I T Y P R O J E C T D A T A
| GREEN BAY (LPD 20) |
3012A-252
ACTIVE PROJECT
|
CLASS: LPD 17 (FLIGHT 1) |
HOMEPORT: SDGO |
PLANNING YARD: HII |
|
| POC: Stephen Ferderer, CNSP N43 |
PHONE: 619-437-2757 |
|
| ENGINEERING WORK SCOPE |
| SURVEY AVAILABILITY: |
FY 17 SRA2-2 |
| SURVEY DATES: |
09/11/2017 - 02/28/2018 |
| SURVEY LOCATION: |
SASBO |
| DESIGN AGENT: |
DELPHINUS |
|
| INSTALLATION WORK SCOPE |
| INSTALL AVAILABILITY: |
FY 25 DSRA2
(749 days) |
| INSTALL DATES: |
02/10/2025 - 03/01/2027
|
| INSTALL LOCATION: |
SDGO |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
12 / 330 |
8 / 34 |
0 / 0 |
0 / 0 |
20 / 364 |
| SANITARY SPACE / FIXTURES: |
21 / 88 |
8 / 15 |
0 / 0 |
0 / 0 |
29 / 103 |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
12 / 330 |
0 / 0 |
0 / 0 |
0 / 0 |
12 / 330 |
| SANITARY SPACE / FIXTURES: |
0 / 0 |
0 / 0 |
0 / 0 |
0 / 0 |
0 / 0 |
|
| OTHER PROJECT: |
|
| PROJECT NO(S): |
BCPO-E7267, BENL-E7268, HCPO-E7345, HENL-E7346 |
| REMARKS: |
|
|
| OTHER PROJ: |
|
| REMARKS: |
LWMB WILL BE INSTALLED VICE SIT-UP BERTHS.
|
|
| HABITABILITY DRAWING NUMBERS |
| DISCIPLINE |
HAB DRAWING NUMBER |
NAVSEA DRAWING NUMBER |
| ARRANGEMENT-BERTHING |
17-LPD 20-01 B |
640 - 8740887 REV B |
| VENTILATION-BERTHING |
17-LPD 20-10 B |
512 - 8740888 REV B |
| ELECTRICAL-BERTHING |
17-LPD 20-30 B |
331 - 8740889 REV B |
NO 52 DWG REQUIRED FOR THIS INSTALLATION REV A ISSUED, NOT INSTALLED. REWORK DRAWINGS FOR LWMB AND ISSUE AS REV B. |
|
| PROJECT NUMBERS(s) AND COMPARTMENTS |
BENL-S4467
3-10-2-L (0)
3-33-0-L (39)
3-33-2-L (27)
3-37-0-L (42)
3-48-0-L (36)
3-53-0-L (39)
3-63-2-L (18)
3-84-1-L (12)
3-95-1-L (21)
3-100-2-L (15)
4-33-2-L (36)
4-80-1-L (45)
PT 12 (330)
|
|
| MILESTONES |
SCHEDULED |
ACTUAL |
EVENTS |
| 04/13/2023 |
09/17/2017 |
09/17/2017
|
START SURVEY |
| 05/12/2023 |
10/05/2017 |
10/05/2017
|
COMPLETE SURVEY |
| 06/13/2023 |
11/03/2017 |
10/18/2017
|
SEND SURVEY REPORT TO PM |
| 05/02/2023 |
05/12/2023 |
05/03/2023
|
TC ISSUE ADVANCE PLANNING NOTICE TO SHIP |
| 06/01/2023 |
06/12/2023 |
05/07/2023
|
SHIP RESPOND TO ADVANCE PLANNING NOTICE |
| 12/18/2023 |
12/18/2023 |
01/19/2024
|
SO SUBMIT DRAWINGS TO PM & PY |
| 12/18/2023 |
12/18/2023 |
01/22/2024
|
SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM |
| 08/14/2024 |
08/14/2024 |
Pending
|
PROJECT MATERIAL PROCUREMENT FUNDED |
| 11/08/2024 |
11/08/2024 |
Pending
|
PROJECT INSTALLATION FUNDED |
| 02/10/2025 |
02/10/2025 |
02/10/2025
|
START AVAILABILITY |
| 02/10/2025 |
02/10/2025 |
02/10/2025
|
START PROJECT |
| 03/01/2027 |
03/01/2027 |
Pending
|
COMPLETE PROJECT |
| 03/01/2027 |
03/01/2027 |
Pending
|
COMPLETE AVAILABILITY |
| Project Record Last Updated: 02/19/2025 |
|