Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM

Select by Ship Name: 

Select by Ship Hull: 

 

MAKIN ISLAND (LHD 8)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
FY 23 SRA2-2   08/21/2023 - 05/10/2025 4 / 294 (b)   12 / 65 (f) 07/10/2018 Complete
  FY 28 DSRA2   11/15/2027 - 09/07/2029 4 / 732 (b)   14 / 135 (f) 10/03/2023 Active
FY 32 SRA3-1   06/14/2032 - 07/27/2033 7 / 403 (b)   15 / 82 (f) 11/15/2027 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
MAKIN ISLAND (LHD 8) 23171-281
ACTIVE PROJECT
CLASS: LHD 1 HOMEPORT: SDGO PLANNING YARD: NNSY
POC: Stephen Ferderer, CNSP N43 PHONE: 619-437-2757
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 23 SRA2-2
SURVEY DATES: 08/21/2023 - 05/10/2025
SURVEY LOCATION: SDGO
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 28 DSRA2     (662 days)
INSTALL DATES: 11/15/2027 - 09/07/2029
INSTALL LOCATION: SDGO
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 4 / 732 0 / 0 0 / 0 0 / 0 4 / 732
SANITARY SPACE / FIXTURES: 14 / 135 0 / 0 0 / 0 0 / 0 14 / 135
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 4 / 732 0 / 0 0 / 0 0 / 0 4 / 732
SANITARY SPACE / FIXTURES: 14 / 135 0 / 0 0 / 0 0 / 0 14 / 135
OTHER PROJECT:
PROJECT NO(S): BENL-E1273, HENL-E1274
REMARKS:
OTHER PROJ:
REMARKS: DRAWINGS SUBMITTAL DATE ACCELERATED TO A-536.
DRAFT APN SENT 2/11/2026.
HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-BERTHING 24-LHD 8-01  - 640 - 8866635  REV -
ARRANGEMENT-SANITARY 24-LHD 8-03  - 644 - 8866636  REV -
VENTILATION-BERTHING 24-LHD 8-10  - 512 - 8866637  REV -
VENTILATION-SANITARY 24-LHD 8-12  - 512 - 8866638  REV -
PIPE-FLUSHING WATER 24-LHD 8-26  - 521 - 8866639  REV -
PIPE-PLUMBING DRAIN 24-LHD 8-27  - 528 - 8866640  REV -
PIPE - POTABLE 24-LHD 8-28  - 533 - 8866641  REV -
ELECTRICAL-BERTHING 24-LHD 8-30  - 331 - 8866642  REV -
ELECTRICAL-SANITARY 24-LHD 8-32  - 331 - 8866643  REV -
ELECTRICAL-POWER SYSTEM 24-LHD 8-39  - 321 - 8866644  REV -
VENTILATION-MFG DET 24-LHD 8-52  - 512 - 8866645  REV -
DRAWINGS SUBMITTAL DATE ACCELERATED TO A-536.
PROJECT NUMBERS(s) AND COMPARTMENTS
BENL-S1273
2-33-0-L (243)
3-25-0-L (132)
3-33-01-L (192)
3-41-0-L (165)
 PT 4 (732)
HENL-S1274
2-39-0-L (18)
2-39.5-0-L (14)
2-39.5-1-L (10)
2-39.5-2-A (1)
3-31-0-L (10)
3-31-2-L (9)
3-32-0-L (5)
3-33-0-L (14)
3-33-1-L (12)
3-33-2-L (8)
3-33-3-A (1)
3-35-2-A (1)
3-41-2-L (7)
3-43-2-L (25)
 PT 14 (135)
MILESTONES SCHEDULED ACTUAL EVENTS
01/15/2026 10/03/2023 10/03/2023 START SURVEY
02/13/2026 10/20/2023 10/20/2023 COMPLETE SURVEY
03/17/2026 11/20/2023 11/15/2023 SEND SURVEY REPORT TO PM
02/03/2026 02/13/2026 02/12/2026 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
03/05/2026 03/05/2026 Pending SHIP RESPOND TO ADVANCE PLANNING NOTICE
09/21/2026 05/29/2026 06/01/2026 SO SUBMIT DRAWINGS TO PM & PY
09/21/2026 05/29/2026 06/02/2026 SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
05/19/2027 05/19/2027 Pending PROJECT MATERIAL PROCUREMENT FUNDED
08/16/2027 08/16/2027 Pending PROJECT INSTALLATION FUNDED
11/15/2027 11/15/2027 Pending START AVAILABILITY
11/15/2027 11/15/2027 Pending START PROJECT
09/07/2029 09/07/2029 Pending COMPLETE PROJECT
09/07/2029 09/07/2029 Pending COMPLETE AVAILABILITY
Project Record Last Updated: 06/02/2026