Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM

Select by Ship Name: 

Select by Ship Hull: 

 

STOCKDALE (DDG 106)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
FY 20 SRA2-1   11/18/2019 - 05/12/2020 6 / 84 (b)   8 / 25 (f) 07/11/2017 Complete
FY 22 SRA2-2   09/26/2022 - 06/05/2023 2 / 135 (b)   4 / 26 (f) 07/11/2017 Complete
  FY 26 DSRA2   04/13/2026 - 06/10/2027 6 / 96 (b)   11 / 34 (f) 07/11/2017 Active
FY 33 DMP   09/19/2033 - 01/24/2036 17 / 40 (b)   13 / 32 (f) 06/04/2026 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
STOCKDALE (DDG 106) 23163-263
ACTIVE PROJECT
CLASS: DDG 51
(Flight IIA Variant)
HOMEPORT: SDGO PLANNING YARD: BATH
POC: Stephen Ferderer, CNSP N43 PHONE: 619-437-2757
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 16 DSRA1
SURVEY DATES: 09/26/2016 - 07/21/2017
SURVEY LOCATION: SDGO
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 26 DSRA2     (423 days)
INSTALL DATES: 04/13/2026 - 06/10/2027
INSTALL LOCATION: SDGO
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 10 / 288 4 / 27 0 / 0 0 / 0 14 / 315
SANITARY SPACE / FIXTURES: 18 / 68 5 / 17 0 / 0 0 / 0 23 / 85
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 2 / 69 4 / 27 0 / 0 0 / 0 6 / 96
SANITARY SPACE / FIXTURES: 6 / 17 5 / 17 0 / 0 0 / 0 11 / 34
OTHER PROJECT:
PROJECT NO(S): BCPO-E6327, BENL-E6328, HCPO-E6329, HENL-E6330
REMARKS:
OTHER PROJ:
REMARKS:
HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-BERTHING 17-DDG 106-01  C 640 - 8740869  REV C
ARRANGEMENT-SANITARY 17-DDG 106-03  C 644 - 8740872  REV C
VENTILATION-BERTHING 17-DDG 106-10  C 512 - 8740870  REV C
VENTILATION-SANITARY 17-DDG 106-12  C 512 - 8740873  REV C
PIPE-SANITARY 17-DDG 106-20  C 505 - 8740874  REV C
ELECTRICAL-BERTHING 17-DDG 106-30  C 331 - 8740871  REV C
ELECTRICAL-SANITARY 17-DDG 106-32  C 331 - 8740875  REV C
VENTILATION-MFG DET 17-DDG 106-52  C 512 - 8740876  REV C
PROJECT NUMBERS(s) AND COMPARTMENTS
BCPO-S6327
1-110-0-L (12)
1-110-1-L (3)
1-115-1-L (3)
2-347-1-L (9)
 PT 4 (27)
BENL-S5384
2-300-01-L (69)
2-314-5-L (0)
 PT 2 (69)
HCPO-S6329
1-110-2-L (7)
1-115-2-A (1)
1-120-1-L (3)
2-338-3-L (5)
2-344-1-A (1)
 PT 5 (17)
HENL-S5374
2-321-2-L (9)
2-326-0-L (4)
2-326-1-L (1)
2-326-2-A (1)
2-333-1-L (1)
2-333-3-L (1)
 PT 6 (17)
MILESTONES SCHEDULED ACTUAL EVENTS
06/13/2024 07/11/2017 07/11/2017 START SURVEY
07/12/2024 07/21/2017 07/28/2017 COMPLETE SURVEY
08/13/2024 08/28/2017 08/16/2017 SEND SURVEY REPORT TO PM
07/02/2024 07/23/2024 07/17/2024 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
08/01/2024 08/01/2024 Pending SHIP RESPOND TO ADVANCE PLANNING NOTICE
02/14/2025 03/10/2025 03/19/2025 SO SUBMIT DRAWINGS TO PM & PY
02/14/2025 03/10/2025 03/19/2025 SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
10/15/2025 10/15/2025 Pending PROJECT MATERIAL PROCUREMENT FUNDED
01/12/2026 01/12/2026 Pending PROJECT INSTALLATION FUNDED
04/13/2026 04/13/2026 04/13/2026 START AVAILABILITY
04/13/2026 04/13/2026 04/13/2026 START PROJECT
06/10/2027 06/10/2027 Pending COMPLETE PROJECT
06/10/2027 06/10/2027 Pending COMPLETE AVAILABILITY
Project Record Last Updated: 04/13/2026