Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM

Select by Ship Name: 

Select by Ship Hull: 

 

DEWEY (DDG 105)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
  FY 26 SRA2-2   03/30/2026 - 12/14/2026 4 / 204 (b)   4 / 17 (f) 04/23/2019 Active
FY 30 DMP   04/01/2030 - 08/05/2032 10 / 111 (b)   13 / 42 (f) 04/20/2026 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
DEWEY (DDG 105) 23162-262
ACTIVE PROJECT
CLASS: DDG 51
(Flight IIA Variant)
HOMEPORT: YOKO PLANNING YARD: BATH
POC: Stephen Ferderer, CNSP N43 PHONE: 619-437-2757
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 19 DSRA1
SURVEY DATES: 02/12/2019 - 11/22/2019
SURVEY LOCATION: SDGO
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 26 SRA2-2     (259 days)
INSTALL DATES: 03/30/2026 - 12/14/2026
INSTALL LOCATION: SRFYOKO
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 11 / 288 5 / 27 0 / 0 0 / 0 16 / 315
SANITARY SPACE / FIXTURES: 16 / 68 5 / 17 0 / 0 0 / 0 21 / 85
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 4 / 204 0 / 0 0 / 0 0 / 0 4 / 204
SANITARY SPACE / FIXTURES: 4 / 17 0 / 0 0 / 0 0 / 0 4 / 17
OTHER PROJECT:
PROJECT NO(S): BCPO-E8294, BENL-E8295, HCPO-E8296, HENL-E8297
REMARKS:
OTHER PROJ:
REMARKS: 04/05/2024 - WORK SCOPE CHANGE REQUESTED BY PE TO CREW BERTHING #1, #2 & #3 AND CREW #3 SANITARY SPACES ONLY. .
HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-BERTHING 19-DDG 105-01  B 640 - 8789073  REV B
ARRANGEMENT-SANITARY 19-DDG 105-03  B 644 - 8789076  REV B
VENTILATION-BERTHING 19-DDG 105-10  B 512 - 8789074  REV B
VENTILATION-SANITARY 19-DDG 105-12  B 512 - 8789077  REV B
PIPE-SANITARY 19-DDG 105-20  B 505 - 8789078  REV B
ELECTRICAL-BERTHING 19-DDG 105-30  B 331 - 8789075  REV B
ELECTRICAL-SANITARY 19-DDG 105-32  B 331 - 8789079  REV B
VENTILATION-MFG DET 19-DDG 105-52  B 512 - 8789080  REV B
REV A ISSUED BUT NOT INSTALLED.
PROJECT NUMBERS(s) AND COMPARTMENTS
BENL-S8295
2-78-01-L (87)
2-300-01-L (60)
2-300-1-L (9)
3-97-02-L (48)
 PT 4 (204)
HENL-S8297
2-321-2-L (9)
2-326-0-L (4)
2-326-1-L (3)
2-326-2-A (1)
 PT 4 (17)
MILESTONES SCHEDULED ACTUAL EVENTS
05/30/2024 04/23/2019 04/23/2019 START SURVEY
06/28/2024 05/04/2019 05/04/2019 COMPLETE SURVEY
07/30/2024 06/04/2019 05/28/2019 SEND SURVEY REPORT TO PM
06/18/2024 06/20/2024 06/24/2024 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
07/18/2024 07/19/2024 10/21/2024 SHIP RESPOND TO ADVANCE PLANNING NOTICE
02/03/2025 12/02/2024 01/13/2025 SO SUBMIT DRAWINGS TO PM & PY
02/03/2025 12/02/2024 01/13/2025 SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
10/01/2025 10/01/2025 Pending PROJECT MATERIAL PROCUREMENT FUNDED
12/29/2025 12/29/2025 Pending PROJECT INSTALLATION FUNDED
03/30/2026 03/30/2026 03/30/2026 START AVAILABILITY
03/30/2026 03/30/2026 03/30/2026 START PROJECT
12/14/2026 12/14/2026 Pending COMPLETE PROJECT
12/14/2026 12/14/2026 Pending COMPLETE AVAILABILITY
Project Record Last Updated: 09/09/2026