Ship Project Status Report
(Blue Book)
Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM
S H I P H A B I T A B I L I T Y P R O J E C T D A T A
| DEWEY (DDG 105) |
23162-262
ACTIVE PROJECT
|
CLASS: DDG 51 (Flight IIA Variant) |
HOMEPORT: YOKO |
PLANNING YARD: BATH |
|
| POC: Stephen Ferderer, CNSP N43 |
PHONE: 619-437-2757 |
|
| ENGINEERING WORK SCOPE |
| SURVEY AVAILABILITY: |
FY 19 DSRA1 |
| SURVEY DATES: |
02/12/2019 - 11/22/2019 |
| SURVEY LOCATION: |
SDGO |
| DESIGN AGENT: |
DELPHINUS |
|
| INSTALLATION WORK SCOPE |
| INSTALL AVAILABILITY: |
FY 26 SRA2-2
(259 days) |
| INSTALL DATES: |
03/30/2026 - 12/14/2026
|
| INSTALL LOCATION: |
SRFYOKO |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
11 / 288 |
5 / 27 |
0 / 0 |
0 / 0 |
16 / 315 |
| SANITARY SPACE / FIXTURES: |
16 / 68 |
5 / 17 |
0 / 0 |
0 / 0 |
21 / 85 |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
4 / 204 |
0 / 0 |
0 / 0 |
0 / 0 |
4 / 204 |
| SANITARY SPACE / FIXTURES: |
4 / 17 |
0 / 0 |
0 / 0 |
0 / 0 |
4 / 17 |
|
| OTHER PROJECT: |
|
| PROJECT NO(S): |
BCPO-E8294, BENL-E8295, HCPO-E8296, HENL-E8297 |
| REMARKS: |
|
|
| OTHER PROJ: |
|
| REMARKS: |
04/05/2024 - WORK SCOPE CHANGE REQUESTED BY PE TO CREW BERTHING #1, #2 & #3 AND CREW #3 SANITARY SPACES ONLY. . |
|
| HABITABILITY DRAWING NUMBERS |
| DISCIPLINE |
HAB DRAWING NUMBER |
NAVSEA DRAWING NUMBER |
| ARRANGEMENT-BERTHING |
19-DDG 105-01 B |
640 - 8789073 REV B |
| ARRANGEMENT-SANITARY |
19-DDG 105-03 B |
644 - 8789076 REV B |
| VENTILATION-BERTHING |
19-DDG 105-10 B |
512 - 8789074 REV B |
| VENTILATION-SANITARY |
19-DDG 105-12 B |
512 - 8789077 REV B |
| PIPE-SANITARY |
19-DDG 105-20 B |
505 - 8789078 REV B |
| ELECTRICAL-BERTHING |
19-DDG 105-30 B |
331 - 8789075 REV B |
| ELECTRICAL-SANITARY |
19-DDG 105-32 B |
331 - 8789079 REV B |
| VENTILATION-MFG DET |
19-DDG 105-52 B |
512 - 8789080 REV B |
| REV A ISSUED BUT NOT INSTALLED. |
|
| PROJECT NUMBERS(s) AND COMPARTMENTS |
BENL-S8295
2-78-01-L (87)
2-300-01-L (60)
2-300-1-L (9)
3-97-02-L (48)
PT 4 (204)
HENL-S8297
2-321-2-L (9)
2-326-0-L (4)
2-326-1-L (3)
2-326-2-A (1)
PT 4 (17)
|
|
| MILESTONES |
SCHEDULED |
ACTUAL |
EVENTS |
| 05/30/2024 |
04/23/2019 |
04/23/2019
|
START SURVEY |
| 06/28/2024 |
05/04/2019 |
05/04/2019
|
COMPLETE SURVEY |
| 07/30/2024 |
06/04/2019 |
05/28/2019
|
SEND SURVEY REPORT TO PM |
| 06/18/2024 |
06/20/2024 |
06/24/2024
|
TC ISSUE ADVANCE PLANNING NOTICE TO SHIP |
| 07/18/2024 |
07/19/2024 |
10/21/2024
|
SHIP RESPOND TO ADVANCE PLANNING NOTICE |
| 02/03/2025 |
12/02/2024 |
01/13/2025
|
SO SUBMIT DRAWINGS TO PM & PY |
| 02/03/2025 |
12/02/2024 |
01/13/2025
|
SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM |
| 10/01/2025 |
10/01/2025 |
Pending
|
PROJECT MATERIAL PROCUREMENT FUNDED |
| 12/29/2025 |
12/29/2025 |
Pending
|
PROJECT INSTALLATION FUNDED |
| 03/30/2026 |
03/30/2026 |
03/30/2026
|
START AVAILABILITY |
| 03/30/2026 |
03/30/2026 |
03/30/2026
|
START PROJECT |
| 12/14/2026 |
12/14/2026 |
Pending
|
COMPLETE PROJECT |
| 12/14/2026 |
12/14/2026 |
Pending
|
COMPLETE AVAILABILITY |
| Project Record Last Updated: 09/09/2026 |
|