Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM

Select by Ship Name: 

Select by Ship Hull: 

 

PEARL HARBOR (LSD 52)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
FY 14 EDPMA   04/16/2014 - 05/27/2016 12 / 210 (b)   7 / 28 (f) 04/04/2011 Complete
FY 18 SRA3-1   05/21/2018 - 05/31/2019 2 / 60 (b)   3 / 15 (f) 04/04/2011 Complete
  FY 26 DSRA4   01/13/2026 - 10/06/2027 8 / 266 (b)   11 / 82 (f) 09/11/2018 Active
FY 30 SRA5-1   02/04/2030 - 02/03/2031 19 / 321 (b)   11 / 38 (f) 01/17/2026 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
PEARL HARBOR (LSD 52) 21959-262
ACTIVE PROJECT
CLASS: LSD 49 HOMEPORT: SDGO PLANNING YARD: PSNSY
POC: Stephen Ferderer, CNSP N43 PHONE: 619-437-2757
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 18 SRA3-1
SURVEY DATES: 05/21/2018 - 05/31/2019
SURVEY LOCATION: SDGO
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 26 DSRA4     (631 days)
INSTALL DATES: 01/13/2026 - 10/06/2027
INSTALL LOCATION: SDGO
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 9 / 270 4 / 25 14 / 292 0 / 0 27 / 587
SANITARY SPACE / FIXTURES: 8 / 60 5 / 17 9 / 43 0 / 0 22 / 120
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 4 / 153 0 / 0 4 / 113 0 / 0 8 / 266
SANITARY SPACE / FIXTURES: 8 / 60 0 / 0 3 / 22 0 / 0 11 / 82
OTHER PROJECT:
PROJECT NO(S): BCPO-E8337, BENL-E8323, BMSG-E8338, BTRM-E8324, HCPO-E8339, HENL-E8325, HTRP-E8326
REMARKS:
OTHER PROJ:
REMARKS:
HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-BERTHING 14-LSD 52-01  C 640 - 8486020  REV C
ARRANGEMENT-SANITARY 14-LSD 52-03  C 644 - 8486023  REV C
VENTILATION-BERTHING 14-LSD 52-10  C 510 - 8486021  REV C
VENTILATION-SANITARY 14-LSD 52-12  C 510 - 8486024  REV C
PIPE-SANITARY 14-LSD 52-20  C 528 - 8486025  REV C
ELECTRICAL-BERTHING 14-LSD 52-30  C 331 - 8486022  REV C
ELECTRICAL-SANITARY 14-LSD 52-32  C 331 - 8486026  REV C
VENTILATION-MFG DET 14-LSD 52-52  C 510 - 8486027  REV C
PROJECT NUMBERS(s) AND COMPARTMENTS
BENL-S8323
04-30-3-L (24)
04-35-3-L (45)
04-35-6-L (42)
04-43-3-L (42)
 PT 4 (153)
BTRM-S8324
03-14-0-L (41)
03-21-0-L (48)
03-21-1-L (12)
03-21-2-L (12)
 PT 4 (113)
HENL-S8325
04-25-0-L (9)
04-25-1-L (6)
04-28-0-L (14)
04-28-01-Q (1)
04-51-3-Q (1)
04-52-4-L (21)
04-55-2-L (7)
04-57-2-Q (1)
 PT 8 (60)
HTRP-S8326
03-19-0-L (17)
03-19-2-Q (1)
03-20-0-L (4)
 PT 3 (22)
MILESTONES SCHEDULED ACTUAL EVENTS
03/15/2024 09/11/2018 09/11/2018 START SURVEY
04/12/2024 09/30/2018 09/30/2018 COMPLETE SURVEY
05/15/2024 10/29/2018 10/29/2018 SEND SURVEY REPORT TO PM
04/03/2024 06/18/2024 06/24/2024 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
05/03/2024 05/03/2024 Pending SHIP RESPOND TO ADVANCE PLANNING NOTICE
11/19/2024 06/03/2024 03/17/2021 SO SUBMIT DRAWINGS TO PM & PY
11/19/2024 06/03/2024 03/17/2021 SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
07/17/2025 07/17/2025 Pending PROJECT MATERIAL PROCUREMENT FUNDED
10/14/2025 10/14/2025 Pending PROJECT INSTALLATION FUNDED
01/13/2026 01/13/2026 01/13/2026 START AVAILABILITY
01/13/2026 01/13/2026 01/13/2026 START PROJECT
10/06/2027 10/06/2027 Pending COMPLETE PROJECT
10/06/2027 10/06/2027 Pending COMPLETE AVAILABILITY
Project Record Last Updated: 01/19/2026