Ship Project Status Report
(Blue Book)
Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM
S H I P H A B I T A B I L I T Y P R O J E C T D A T A
| PEARL HARBOR (LSD 52) |
21959-262
ACTIVE PROJECT
|
| CLASS: LSD 49 |
HOMEPORT: SDGO |
PLANNING YARD: PSNSY |
|
| POC: Stephen Ferderer, CNSP N43 |
PHONE: 619-437-2757 |
|
| ENGINEERING WORK SCOPE |
| SURVEY AVAILABILITY: |
FY 18 SRA3-1 |
| SURVEY DATES: |
05/21/2018 - 05/31/2019 |
| SURVEY LOCATION: |
SDGO |
| DESIGN AGENT: |
DELPHINUS |
|
| INSTALLATION WORK SCOPE |
| INSTALL AVAILABILITY: |
FY 26 DSRA4
(631 days) |
| INSTALL DATES: |
01/13/2026 - 10/06/2027
|
| INSTALL LOCATION: |
SDGO |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
9 / 270 |
4 / 25 |
14 / 292 |
0 / 0 |
27 / 587 |
| SANITARY SPACE / FIXTURES: |
8 / 60 |
5 / 17 |
9 / 43 |
0 / 0 |
22 / 120 |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
4 / 153 |
0 / 0 |
4 / 113 |
0 / 0 |
8 / 266 |
| SANITARY SPACE / FIXTURES: |
8 / 60 |
0 / 0 |
3 / 22 |
0 / 0 |
11 / 82 |
|
| OTHER PROJECT: |
|
| PROJECT NO(S): |
BCPO-E8337, BENL-E8323, BMSG-E8338, BTRM-E8324, HCPO-E8339, HENL-E8325, HTRP-E8326 |
| REMARKS: |
|
|
|
| HABITABILITY DRAWING NUMBERS |
| DISCIPLINE |
HAB DRAWING NUMBER |
NAVSEA DRAWING NUMBER |
| ARRANGEMENT-BERTHING |
14-LSD 52-01 C |
640 - 8486020 REV C |
| ARRANGEMENT-SANITARY |
14-LSD 52-03 C |
644 - 8486023 REV C |
| VENTILATION-BERTHING |
14-LSD 52-10 C |
510 - 8486021 REV C |
| VENTILATION-SANITARY |
14-LSD 52-12 C |
510 - 8486024 REV C |
| PIPE-SANITARY |
14-LSD 52-20 C |
528 - 8486025 REV C |
| ELECTRICAL-BERTHING |
14-LSD 52-30 C |
331 - 8486022 REV C |
| ELECTRICAL-SANITARY |
14-LSD 52-32 C |
331 - 8486026 REV C |
| VENTILATION-MFG DET |
14-LSD 52-52 C |
510 - 8486027 REV C |
|
| PROJECT NUMBERS(s) AND COMPARTMENTS |
BENL-S8323
04-30-3-L (24)
04-35-3-L (45)
04-35-6-L (42)
04-43-3-L (42)
PT 4 (153)
BTRM-S8324
03-14-0-L (41)
03-21-0-L (48)
03-21-1-L (12)
03-21-2-L (12)
PT 4 (113)
HENL-S8325
04-25-0-L (9)
04-25-1-L (6)
04-28-0-L (14)
04-28-01-Q (1)
04-51-3-Q (1)
04-52-4-L (21)
04-55-2-L (7)
04-57-2-Q (1)
PT 8 (60)
HTRP-S8326
03-19-0-L (17)
03-19-2-Q (1)
03-20-0-L (4)
PT 3 (22)
|
|
| MILESTONES |
SCHEDULED |
ACTUAL |
EVENTS |
| 03/15/2024 |
09/11/2018 |
09/11/2018
|
START SURVEY |
| 04/12/2024 |
09/30/2018 |
09/30/2018
|
COMPLETE SURVEY |
| 05/15/2024 |
10/29/2018 |
10/29/2018
|
SEND SURVEY REPORT TO PM |
| 04/03/2024 |
06/18/2024 |
06/24/2024
|
TC ISSUE ADVANCE PLANNING NOTICE TO SHIP |
| 05/03/2024 |
05/03/2024 |
Pending
|
SHIP RESPOND TO ADVANCE PLANNING NOTICE |
| 11/19/2024 |
06/03/2024 |
03/17/2021
|
SO SUBMIT DRAWINGS TO PM & PY |
| 11/19/2024 |
06/03/2024 |
03/17/2021
|
SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM |
| 07/17/2025 |
07/17/2025 |
Pending
|
PROJECT MATERIAL PROCUREMENT FUNDED |
| 10/14/2025 |
10/14/2025 |
Pending
|
PROJECT INSTALLATION FUNDED |
| 01/13/2026 |
01/13/2026 |
01/13/2026
|
START AVAILABILITY |
| 01/13/2026 |
01/13/2026 |
01/13/2026
|
START PROJECT |
| 10/06/2027 |
10/06/2027 |
Pending
|
COMPLETE PROJECT |
| 10/06/2027 |
10/06/2027 |
Pending
|
COMPLETE AVAILABILITY |
| Project Record Last Updated: 01/19/2026 |
|