Ship Project Status Report
(Blue Book)
Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM
S H I P H A B I T A B I L I T Y P R O J E C T D A T A
| OKANE (DDG 77) |
21951-262
ACTIVE PROJECT
|
CLASS: DDG 51 (Flight II Variant) |
HOMEPORT: SDGO |
PLANNING YARD: BATH |
|
| POC: Stephen Ferderer, CNSP N43 |
PHONE: 619-437-2757 |
|
| ENGINEERING WORK SCOPE |
| SURVEY AVAILABILITY: |
FY 10 SRA2-1 |
| SURVEY DATES: |
04/07/2010 - 06/19/2010 |
| SURVEY LOCATION: |
PEARL |
| DESIGN AGENT: |
DELPHINUS |
|
| INSTALLATION WORK SCOPE |
| INSTALL AVAILABILITY: |
FY 26 DSRA3
(409 days) |
| INSTALL DATES: |
02/02/2026 - 03/18/2027
|
| INSTALL LOCATION: |
SDGO |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
6 / 204 |
0 / 0 |
0 / 0 |
0 / 0 |
6 / 204 |
| SANITARY SPACE / FIXTURES: |
12 / 50 |
0 / 0 |
0 / 0 |
0 / 0 |
12 / 50 |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
5 / 81 |
0 / 0 |
0 / 0 |
0 / 0 |
5 / 81 |
| SANITARY SPACE / FIXTURES: |
8 / 25 |
0 / 0 |
0 / 0 |
0 / 0 |
8 / 25 |
|
| OTHER PROJECT: |
|
| PROJECT NO(S): |
BENL-E0400, HENL-E0401 |
| REMARKS: |
|
|
| OTHER PROJ: |
|
| REMARKS: |
DRAFT APN SENT 4/30/2024. |
|
| HABITABILITY DRAWING NUMBERS |
| DISCIPLINE |
HAB DRAWING NUMBER |
NAVSEA DRAWING NUMBER |
| ARRANGEMENT-BERTHING |
12-DDG 77-01 D |
640 - 8470053 REV D |
| ARRANGEMENT-SANITARY |
12-DDG 77-03 D |
644 - 8470056 REV D |
| VENTILATION-BERTHING |
12-DDG 77-10 D |
512 - 8470054 REV D |
| VENTILATION-SANITARY |
12-DDG 77-12 D |
512 - 8470057 REV D |
| PIPE-SANITARY |
12-DDG 77-20 D |
505 - 8470058 REV D |
| ELECTRICAL-BERTHING |
12-DDG 77-30 D |
331 - 8470055 REV D |
| ELECTRICAL-SANITARY |
12-DDG 77-32 D |
331 - 8470059 REV D |
| VALIDATION OF REV A INSTALLATION DRAWINGS COMPLETED. 52 DWG FOR REV D NOT REQUIRED FOR THIS INSTALLATION. |
|
| PROJECT NUMBERS(s) AND COMPARTMENTS |
BENL-S5087
3-300-1-L (24)
3-310-2-L (21)
3-326-1-L (0)
3-338-1-L (18)
3-338-2-L (18)
PT 5 (81)
HENL-S5309
3-300-2-L (5)
3-306-2-A (1)
3-325-1-L (6)
3-335-1-A (1)
3-338-3-A (1)
3-338-4-A (1)
3-338-5-L (5)
3-338-6-L (5)
PT 8 (25)
|
|
| MILESTONES |
SCHEDULED |
ACTUAL |
EVENTS |
| 04/04/2024 |
05/04/2010 |
05/07/2010
|
START SURVEY |
| 05/03/2024 |
05/12/2010 |
05/14/2010
|
COMPLETE SURVEY |
| 06/04/2024 |
06/11/2010 |
06/14/2010
|
SEND SURVEY REPORT TO PM |
| 04/23/2024 |
05/02/2024 |
05/01/2024
|
TC ISSUE ADVANCE PLANNING NOTICE TO SHIP |
| 05/23/2024 |
05/23/2024 |
Pending
|
SHIP RESPOND TO ADVANCE PLANNING NOTICE |
| 12/09/2024 |
11/08/2024 |
12/09/2024
|
SO SUBMIT DRAWINGS TO PM & PY |
| 12/09/2024 |
11/08/2024 |
12/09/2024
|
SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM |
| 08/06/2025 |
08/06/2025 |
Pending
|
PROJECT MATERIAL PROCUREMENT FUNDED |
| 11/03/2025 |
11/03/2025 |
Pending
|
PROJECT INSTALLATION FUNDED |
| 02/02/2026 |
02/02/2026 |
02/02/2026
|
START AVAILABILITY |
| 02/02/2026 |
02/02/2026 |
02/02/2026
|
START PROJECT |
| 03/18/2027 |
03/18/2027 |
Pending
|
COMPLETE PROJECT |
| 03/18/2027 |
03/18/2027 |
Pending
|
COMPLETE AVAILABILITY |
| Project Record Last Updated: 02/03/2026 |
|