Ship Project Status Report
(Blue Book)
Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM
S H I P H A B I T A B I L I T Y P R O J E C T D A T A
| DECATUR (DDG 73) |
21947-281A
ACTIVE PROJECT
|
CLASS: DDG 51 (Flight II Variant) |
HOMEPORT: PEARL |
PLANNING YARD: BATH |
|
| POC: Stephen Ferderer, CNSP N43 |
PHONE: 619-437-2757 |
|
| ENGINEERING WORK SCOPE |
| SURVEY AVAILABILITY: |
FY 24 SRA3-1 |
| SURVEY DATES: |
05/06/2024 - 03/14/2025 |
| SURVEY LOCATION: |
PEARL |
| DESIGN AGENT: |
DELPHINUS |
|
| INSTALLATION WORK SCOPE |
| INSTALL AVAILABILITY: |
FY 28 DSRA5
(397 days) |
| INSTALL DATES: |
10/04/2027 - 11/04/2028
|
| INSTALL LOCATION: |
PEARL |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
1 / 42 |
0 / 0 |
0 / 0 |
0 / 0 |
1 / 42 |
| SANITARY SPACE / FIXTURES: |
2 / 11 |
0 / 0 |
0 / 0 |
0 / 0 |
2 / 11 |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
1 / 42 |
0 / 0 |
0 / 0 |
0 / 0 |
1 / 42 |
| SANITARY SPACE / FIXTURES: |
2 / 11 |
0 / 0 |
0 / 0 |
0 / 0 |
2 / 11 |
|
| OTHER PROJECT: |
|
| PROJECT NO(S): |
BENL-E7365, HENL-E7366 |
| REMARKS: |
DESIGN VERIFICATION REQUIRED FOR CREW COMPLEX #2. ORIGINALLY DESIGNED IN FY 11. INSTALLED IN FY 14. |
|
| OTHER PROJ: |
INSTALL WITH 21947-281B |
| REMARKS: |
CREW COMPLEX 2 |
|
| HABITABILITY DRAWING NUMBERS |
| DISCIPLINE |
HAB DRAWING NUMBER |
NAVSEA DRAWING NUMBER |
| ARRANGEMENT-BERTHING |
14-DDG 73-01 E |
640 - 8486052 REV E |
| ARRANGEMENT-SANITARY |
14-DDG 73-03 E |
644 - 8486055 REV E |
| VENTILATION-BERTHING |
14-DDG 73-10 E |
512 - 8486053 REV E |
| VENTILATION-SANITARY |
14-DDG 73-12 E |
512 - 8486056 REV E |
| PIPE-SANITARY |
14-DDG 73-20 E |
505 - 8486057 REV E |
| ELECTRICAL-BERTHING |
14-DDG 73-30 E |
331 - 8486054 REV E |
| ELECTRICAL-SANITARY |
14-DDG 73-32 E |
331 - 8486058 REV E |
| VENTILATION-MFG DET |
14-DDG 73-52 E |
512 - 8486059 REV E |
|
| PROJECT NUMBERS(s) AND COMPARTMENTS |
BENL-S7365
3-97-02-L (42)
PT 1 (42)
HENL-S7366
3-97-01-L (10)
3-102-1-A (1)
PT 2 (11)
|
|
| MILESTONES |
SCHEDULED |
ACTUAL |
EVENTS |
| 12/04/2025 |
07/24/2024 |
07/24/2024
|
START SURVEY |
| 01/02/2026 |
08/07/2024 |
08/07/2024
|
COMPLETE SURVEY |
| 02/03/2026 |
09/06/2024 |
09/06/2024
|
SEND SURVEY REPORT TO PM |
| 12/23/2025 |
12/23/2025 |
12/22/2025
|
TC ISSUE ADVANCE PLANNING NOTICE TO SHIP |
| 01/22/2026 |
01/22/2026 |
Pending
|
SHIP RESPOND TO ADVANCE PLANNING NOTICE |
| 08/10/2026 |
08/10/2026 |
08/10/2026
|
SO SUBMIT DRAWINGS TO PM & PY |
| 08/10/2026 |
08/10/2026 |
08/10/2026
|
SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM |
| 04/07/2027 |
04/07/2027 |
Pending
|
PROJECT MATERIAL PROCUREMENT FUNDED |
| 07/02/2027 |
07/02/2027 |
Pending
|
PROJECT INSTALLATION FUNDED |
| 10/04/2027 |
10/04/2027 |
Pending
|
START AVAILABILITY |
| 10/04/2027 |
10/04/2027 |
Pending
|
START PROJECT |
| 11/04/2028 |
11/04/2028 |
Pending
|
COMPLETE PROJECT |
| 11/04/2028 |
11/04/2028 |
Pending
|
COMPLETE AVAILABILITY |
| Project Record Last Updated: 09/01/2026 |
|