Ship Project Status Report
(Blue Book)
Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM
S H I P H A B I T A B I L I T Y P R O J E C T D A T A
| BENFOLD (DDG 65) |
21940-271
ACTIVE PROJECT
|
CLASS: DDG 51 (Flight I Variant) |
HOMEPORT: EVERETT |
PLANNING YARD: BATH |
|
| POC: Stephen Ferderer, CNSP N43 |
PHONE: 619-437-2757 |
|
| ENGINEERING WORK SCOPE |
| SURVEY AVAILABILITY: |
FY 19 DSRA4 |
| SURVEY DATES: |
04/10/2019 - 06/15/2020 |
| SURVEY LOCATION: |
SRFYOKO |
| DESIGN AGENT: |
DELPHINUS |
|
| INSTALLATION WORK SCOPE |
| INSTALL AVAILABILITY: |
FY 27 SRA5-2
(266 days) |
| INSTALL DATES: |
11/30/2026 - 08/23/2027
|
| INSTALL LOCATION: |
EVER |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
7 / 210 |
0 / 0 |
0 / 0 |
16 / 39 |
23 / 249 |
| SANITARY SPACE / FIXTURES: |
12 / 39 |
0 / 0 |
0 / 0 |
8 / 25 |
20 / 64 |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
5 / 78 |
0 / 0 |
0 / 0 |
0 / 0 |
5 / 78 |
| SANITARY SPACE / FIXTURES: |
4 / 12 |
0 / 0 |
0 / 0 |
0 / 0 |
4 / 12 |
|
| OTHER PROJECT: |
|
| PROJECT NO(S): |
BENL-E9409, BOFF-E9411, HENL-E9410, HOFF-E9412 |
| REMARKS: |
|
|
| OTHER PROJ: |
|
| REMARKS: |
CREW BERTHING #4, #5, #6 & #7. CREW SANITARY #5 AND #6. CREW SANITARY #3 AND #7 INSTALLED FY 19 USING MILIUS DRAWINGS. |
|
| HABITABILITY DRAWING NUMBERS |
| DISCIPLINE |
HAB DRAWING NUMBER |
NAVSEA DRAWING NUMBER |
| ARRANGEMENT-BERTHING |
13-DDG 65-01 E |
640 - 8486028 REV E |
| ARRANGEMENT-SANITARY |
13-DDG 65-03 E |
644 - 8486031 REV E |
| VENTILATION-BERTHING |
13-DDG 65-10 E |
512 - 8486029 REV E |
| VENTILATION-SANITARY |
13-DDG 65-12 E |
512 - 8486032 REV E |
| PIPE-SANITARY |
13-DDG 65-20 E |
505 - 8486033 REV E |
| ELECTRICAL-BERTHING |
13-DDG 65-30 E |
331 - 8486030 REV E |
| ELECTRICAL-SANITARY |
13-DDG 65-32 E |
331 - 8486034 REV E |
| VENTILATION-MFG DET |
13-DDG 65-52 E |
512 - 8486035 REV E |
| REV D SANITARY ISSUED 12/21/2022, BUT NOT INSTALLED. REV D SANITARY SPACES WILL BE INCORPARTED INTO REV E DRAWINGS |
|
| PROJECT NUMBERS(s) AND COMPARTMENTS |
BENL-S7349
3-300-1-L (24)
3-310-2-L (18)
3-326-1-L (0)
3-338-1-L (18)
3-338-2-L (18)
PT 5 (78)
HENL-S7350
3-300-2-L (5)
3-306-2-A (1)
3-338-3-A (1)
3-338-5-L (5)
PT 4 (12)
|
|
| MILESTONES |
SCHEDULED |
ACTUAL |
EVENTS |
| 01/30/2025 |
09/11/2019 |
09/11/2019
|
START SURVEY |
| 02/28/2025 |
09/26/2019 |
09/26/2019
|
COMPLETE SURVEY |
| 04/01/2025 |
10/25/2019 |
10/25/2019
|
SEND SURVEY REPORT TO PM |
| 02/18/2025 |
09/25/2024 |
09/23/2024
|
TC ISSUE ADVANCE PLANNING NOTICE TO SHIP |
| 03/20/2025 |
03/20/2025 |
Pending
|
SHIP RESPOND TO ADVANCE PLANNING NOTICE |
| 10/06/2025 |
10/06/2025 |
10/08/2025
|
SO SUBMIT DRAWINGS TO PM & PY |
| 10/06/2025 |
10/06/2025 |
10/08/2025
|
SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM |
| 06/03/2026 |
06/03/2026 |
Pending
|
PROJECT MATERIAL PROCUREMENT FUNDED |
| 08/31/2026 |
08/31/2026 |
Pending
|
PROJECT INSTALLATION FUNDED |
| 11/30/2026 |
11/30/2026 |
Pending
|
START AVAILABILITY |
| 11/30/2026 |
11/30/2026 |
Pending
|
START PROJECT |
| 08/23/2027 |
08/23/2027 |
Pending
|
COMPLETE PROJECT |
| 08/23/2027 |
08/23/2027 |
Pending
|
COMPLETE AVAILABILITY |
| Project Record Last Updated: 05/12/2026 |
|