Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM

Select by Ship Name: 

Select by Ship Hull: 

 

HARPERS FERRY (LSD 49)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
FY 11 EDPMA   07/13/2011 - 12/03/2012 4 / 123 (b)   4 / 28 (f) 09/28/2007 Complete
FY 17 PMA3-2   12/05/2016 - 03/30/2018 8 / 153 (b)   8 / 31 (f) 08/23/2011 Complete
FY 20 DSRA2   02/24/2020 - 08/09/2021 8 / 78 (b)   5 / 19 (f) 08/05/2014 Complete
FY 20 DSRA2   02/24/2020 - 08/09/2021 3 / 60 (b)   3 / 15 (f) 08/23/2011 Complete
  FY 25 SRA4-1   07/28/2025 - 04/19/2027 2 / 84 (b)   3 / 31 (f) 02/06/2024 Active
FY 25 SRA4-1   07/28/2025 - 04/19/2027 0 / 0 (b)   4 / 20 (f) 08/23/2011 Active
FY 29 SRA4-2   02/09/2029 - 02/08/2030 7 / 122 (b)   0 / 0 (f) 08/16/2026 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
HARPERS FERRY (LSD 49) 21852-254A
ACTIVE PROJECT
CLASS: LSD 49 HOMEPORT: SDGO PLANNING YARD: PSNSY
POC: Stephen Ferderer, CNSP N43 PHONE: 619-437-2757
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 24 CMAV
SURVEY DATES: 01/29/2024 - 03/01/2024
SURVEY LOCATION: SDGO
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 25 SRA4-1     (630 days)
INSTALL DATES: 07/28/2025 - 04/19/2027
INSTALL LOCATION: SDGO
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 2 / 64 0 / 0 0 / 0 0 / 0 2 / 64
SANITARY SPACE / FIXTURES: 3 / 31 0 / 0 0 / 0 0 / 0 3 / 31
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 2 / 84 0 / 0 0 / 0 0 / 0 2 / 84
SANITARY SPACE / FIXTURES: 3 / 31 0 / 0 0 / 0 0 / 0 3 / 31
OTHER PROJECT:
PROJECT NO(S): BENL-E4337, HENL-E4370
REMARKS:
OTHER PROJ: INSTALL WITH 21852-254B
REMARKS:
HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-BERTHING 14-LSD 49-01  C 643 - 8486044  REV C
ARRANGEMENT-SANITARY 14-LSD 49-03  C 644 - 8486047  REV C
VENTILATION-BERTHING 14-LSD 49-10  C 510 - 8486045  REV C
VENTILATION-SANITARY 14-LSD 49-12  C 510 - 8486048  REV C
PIPE-SANITARY 14-LSD 49-20  C 505 - 8486049  REV C
ELECTRICAL-BERTHING 14-LSD 49-30  C 331 - 8486046  REV C
ELECTRICAL-SANITARY 14-LSD 49-32  C 331 - 8486050  REV C
VENTILATION-MFG DET 14-LSD 49-52  C 510 - 8486051  REV C
PROJECT NUMBERS(s) AND COMPARTMENTS
BENL-S4337
04-35-6-L (42)
04-43-3-L (42)
 PT 2 (84)
HENL-S4370
04-52-4-L (19)
04-55-2-L (11)
04-57-2-Q (1)
 PT 3 (31)
MILESTONES SCHEDULED ACTUAL EVENTS
09/28/2023 02/06/2024 02/06/2024 START SURVEY
10/27/2023 02/10/2024 02/10/2024 COMPLETE SURVEY
11/28/2023 03/11/2024 03/29/2024 SEND SURVEY REPORT TO PM
10/17/2023 04/04/2024 04/04/2024 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
11/16/2023 05/03/2024 04/22/2024 SHIP RESPOND TO ADVANCE PLANNING NOTICE
06/03/2024 06/03/2024 06/10/2024 SO SUBMIT DRAWINGS TO PM & PY
06/03/2024 06/03/2024 06/11/2024 SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
01/29/2025 01/29/2025 Pending PROJECT MATERIAL PROCUREMENT FUNDED
04/28/2025 04/28/2025 Pending PROJECT INSTALLATION FUNDED
07/28/2025 07/28/2025 07/28/2025 START AVAILABILITY
07/28/2025 07/28/2025 07/28/2025 START PROJECT
04/19/2027 04/19/2027 Pending COMPLETE PROJECT
04/19/2027 04/19/2027 Pending COMPLETE AVAILABILITY
Project Record Last Updated: 07/28/2025