Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM

Select by Ship Name: 

Select by Ship Hull: 

 

JOHN S MCCAIN (DDG 56)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
FY 10 SRA9   10/07/2009 - 12/09/2009 1 / 42 (b)   2 / 10 (f) 01/20/2008 Complete
FY 13 SRA2-1   05/01/2013 - 08/14/2013 2 / 171 (b)   0 / 0 (f) 09/28/2011 Complete
FY 15 EDSRA   03/25/2015 - 06/04/2016 19 / 49 (b)   16 / 57 (f) NA Complete
FY 18 EDMAV   12/13/2017 - 11/05/2019 7 / 240 (b)   13 / 54 (f) NA Complete
FY 25 DSRA4   02/11/2025 - 05/08/2026 2 / 123 (b)   2 / 15 (f) 04/19/2022 Complete
  FY 28 ISRA6-1   07/31/2028 - 12/27/2028 4 / 27 (b)   5 / 17 (f) 04/19/2022 Active
FY 30 ISRA6-2   10/29/2029 - 03/27/2030 5 / 33 (b)   0 / 0 (f) 07/31/2028 Active
FY 31 DSRA6   09/15/2031 - 08/15/2032 16 / 39 (b)   8 / 25 (f) 10/29/2029 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
JOHN S MCCAIN (DDG 56) 21686-284
ACTIVE PROJECT
CLASS: DDG 51
(Flight I Variant)
HOMEPORT: EVERETT PLANNING YARD: BATH
POC: Stephen Ferderer, CNSP N43 PHONE: 619-437-2757
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 22 SRA4-1
SURVEY DATES: 01/10/2022 - 10/21/2022
SURVEY LOCATION: EVER
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 28 ISRA6-1     (149 days)
INSTALL DATES: 07/31/2028 - 12/27/2028
INSTALL LOCATION: EVER
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 2 / 123 4 / 27 0 / 0 0 / 0 6 / 150
SANITARY SPACE / FIXTURES: 2 / 15 5 / 17 0 / 0 0 / 0 7 / 32
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 0 / 0 4 / 27 0 / 0 0 / 0 4 / 27
SANITARY SPACE / FIXTURES: 0 / 0 5 / 17 0 / 0 0 / 0 5 / 17
OTHER PROJECT:
PROJECT NO(S): BCPO-E1167, HCPO-E1279, BENL-E1358, HENL-E1359
REMARKS:
OTHER PROJ:
REMARKS:
HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-BERTHING 22-DDG 56-01  B 640 - 8866681  REV B
ARRANGEMENT-SANITARY 22-DDG 56-03  B 644 - 8866682  REV B
VENTILATION-BERTHING 22-DDG 56-10  B 512 - 8866683  REV B
VENTILATION-SANITARY 22-DDG 56-12  B 512 - 8866684  REV B
PIPE-SANITARY 22-DDG 56-20  B 505 - 8866685  REV B
ELECTRICAL-BERTHING 22-DDG 56-30  B 331 - 8866686  REV B
ELECTRICAL-SANITARY 22-DDG 56-32  B 331 - 8866687  REV B
VENTILATION-MFG DET 22-DDG 56-52  B 512 - 8866688  REV B
PROJECT NUMBERS(s) AND COMPARTMENTS
BCPO-S1167
1-110-0-L (12)
1-110-1-L (3)
1-115-1-L (3)
2-347-1-L (9)
 PT 4 (27)
HCPO-S1279
1-110-2-L (7)
1-115-2-A (1)
1-120-1-L (3)
2-338-3-L (5)
2-344-1-A (1)
 PT 5 (17)
MILESTONES SCHEDULED ACTUAL EVENTS
10/01/2026 04/19/2022 04/19/2022 START SURVEY
10/30/2026 04/26/2022 04/26/2022 COMPLETE SURVEY
12/01/2026 05/26/2022 05/09/2022 SEND SURVEY REPORT TO PM
10/20/2026 10/20/2026 Pending TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
11/19/2026 11/19/2026 Pending SHIP RESPOND TO ADVANCE PLANNING NOTICE
06/07/2027 06/07/2027 Pending SO SUBMIT DRAWINGS TO PM & PY
06/07/2027 06/07/2027 Pending SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
02/02/2028 02/02/2028 Pending PROJECT MATERIAL PROCUREMENT FUNDED
05/01/2028 05/01/2028 Pending PROJECT INSTALLATION FUNDED
07/31/2028 07/31/2028 Pending START AVAILABILITY
07/31/2028 07/31/2028 Pending START PROJECT
12/27/2028 12/27/2028 Pending COMPLETE PROJECT
12/27/2028 12/27/2028 Pending COMPLETE AVAILABILITY
Project Record Last Updated: 09/09/2026