Ship Project Status Report
(Blue Book)
Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM
S H I P H A B I T A B I L I T Y P R O J E C T D A T A
| JOHN S MCCAIN (DDG 56) |
21686-284
ACTIVE PROJECT
|
CLASS: DDG 51 (Flight I Variant) |
HOMEPORT: EVERETT |
PLANNING YARD: BATH |
|
| POC: Stephen Ferderer, CNSP N43 |
PHONE: 619-437-2757 |
|
| ENGINEERING WORK SCOPE |
| SURVEY AVAILABILITY: |
FY 22 SRA4-1 |
| SURVEY DATES: |
01/10/2022 - 10/21/2022 |
| SURVEY LOCATION: |
EVER |
| DESIGN AGENT: |
DELPHINUS |
|
| INSTALLATION WORK SCOPE |
| INSTALL AVAILABILITY: |
FY 28 ISRA6-1
(149 days) |
| INSTALL DATES: |
07/31/2028 - 12/27/2028
|
| INSTALL LOCATION: |
EVER |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
2 / 123 |
4 / 27 |
0 / 0 |
0 / 0 |
6 / 150 |
| SANITARY SPACE / FIXTURES: |
2 / 15 |
5 / 17 |
0 / 0 |
0 / 0 |
7 / 32 |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
0 / 0 |
4 / 27 |
0 / 0 |
0 / 0 |
4 / 27 |
| SANITARY SPACE / FIXTURES: |
0 / 0 |
5 / 17 |
0 / 0 |
0 / 0 |
5 / 17 |
|
| OTHER PROJECT: |
|
| PROJECT NO(S): |
BCPO-E1167, HCPO-E1279, BENL-E1358, HENL-E1359 |
| REMARKS: |
|
|
|
| HABITABILITY DRAWING NUMBERS |
| DISCIPLINE |
HAB DRAWING NUMBER |
NAVSEA DRAWING NUMBER |
| ARRANGEMENT-BERTHING |
22-DDG 56-01 B |
640 - 8866681 REV B |
| ARRANGEMENT-SANITARY |
22-DDG 56-03 B |
644 - 8866682 REV B |
| VENTILATION-BERTHING |
22-DDG 56-10 B |
512 - 8866683 REV B |
| VENTILATION-SANITARY |
22-DDG 56-12 B |
512 - 8866684 REV B |
| PIPE-SANITARY |
22-DDG 56-20 B |
505 - 8866685 REV B |
| ELECTRICAL-BERTHING |
22-DDG 56-30 B |
331 - 8866686 REV B |
| ELECTRICAL-SANITARY |
22-DDG 56-32 B |
331 - 8866687 REV B |
| VENTILATION-MFG DET |
22-DDG 56-52 B |
512 - 8866688 REV B |
|
| PROJECT NUMBERS(s) AND COMPARTMENTS |
BCPO-S1167
1-110-0-L (12)
1-110-1-L (3)
1-115-1-L (3)
2-347-1-L (9)
PT 4 (27)
HCPO-S1279
1-110-2-L (7)
1-115-2-A (1)
1-120-1-L (3)
2-338-3-L (5)
2-344-1-A (1)
PT 5 (17)
|
|
| MILESTONES |
SCHEDULED |
ACTUAL |
EVENTS |
| 10/01/2026 |
04/19/2022 |
04/19/2022
|
START SURVEY |
| 10/30/2026 |
04/26/2022 |
04/26/2022
|
COMPLETE SURVEY |
| 12/01/2026 |
05/26/2022 |
05/09/2022
|
SEND SURVEY REPORT TO PM |
| 10/20/2026 |
10/20/2026 |
Pending
|
TC ISSUE ADVANCE PLANNING NOTICE TO SHIP |
| 11/19/2026 |
11/19/2026 |
Pending
|
SHIP RESPOND TO ADVANCE PLANNING NOTICE |
| 06/07/2027 |
06/07/2027 |
Pending
|
SO SUBMIT DRAWINGS TO PM & PY |
| 06/07/2027 |
06/07/2027 |
Pending
|
SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM |
| 02/02/2028 |
02/02/2028 |
Pending
|
PROJECT MATERIAL PROCUREMENT FUNDED |
| 05/01/2028 |
05/01/2028 |
Pending
|
PROJECT INSTALLATION FUNDED |
| 07/31/2028 |
07/31/2028 |
Pending
|
START AVAILABILITY |
| 07/31/2028 |
07/31/2028 |
Pending
|
START PROJECT |
| 12/27/2028 |
12/27/2028 |
Pending
|
COMPLETE PROJECT |
| 12/27/2028 |
12/27/2028 |
Pending
|
COMPLETE AVAILABILITY |
| Project Record Last Updated: 09/09/2026 |
|