Ship Project Status Report
(Blue Book)
Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM
S H I P H A B I T A B I L I T Y P R O J E C T D A T A
| CURTIS WILBUR (DDG 54) |
21640-261
ACTIVE PROJECT
|
CLASS: DDG 51 (Flight I Variant) |
HOMEPORT: SDGO |
PLANNING YARD: BATH |
|
| POC: Stephen Ferderer, CNSP N43 |
PHONE: 619-437-2757 |
|
| ENGINEERING WORK SCOPE |
| SURVEY AVAILABILITY: |
FY 19 SRA3-2 |
| SURVEY DATES: |
07/15/2019 - 04/07/2020 |
| SURVEY LOCATION: |
SRFYOKO |
| DESIGN AGENT: |
DELPHINUS |
|
| INSTALLATION WORK SCOPE |
| INSTALL AVAILABILITY: |
FY 26 SRA4-1
(295 days) |
| INSTALL DATES: |
12/08/2025 - 09/29/2026
|
| INSTALL LOCATION: |
SDGO |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
3 / 213 |
0 / 0 |
0 / 0 |
0 / 0 |
3 / 213 |
| SANITARY SPACE / FIXTURES: |
5 / 35 |
0 / 0 |
0 / 0 |
0 / 0 |
5 / 35 |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
1 / 75 |
0 / 0 |
0 / 0 |
0 / 0 |
1 / 75 |
| SANITARY SPACE / FIXTURES: |
2 / 15 |
0 / 0 |
0 / 0 |
0 / 0 |
2 / 15 |
|
| OTHER PROJECT: |
|
| PROJECT NO(S): |
BENL-E9384, HENL-E9385 |
| REMARKS: |
|
|
| OTHER PROJ: |
|
| REMARKS: |
CREW COMPLEX # 1 |
|
| HABITABILITY DRAWING NUMBERS |
| DISCIPLINE |
HAB DRAWING NUMBER |
NAVSEA DRAWING NUMBER |
| ARRANGEMENT-BERTHING |
19-DDG 54-01 B |
640 - 8866521 REV B |
| ARRANGEMENT-SANITARY |
19-DDG 54-03 B |
644 - 8866522 REV B |
| VENTILATION-BERTHING |
19-DDG 54-10 B |
512 - 8866523 REV B |
| VENTILATION-SANITARY |
19-DDG 54-12 B |
512 - 8866524 REV B |
| PIPE-SANITARY |
19-DDG 54-20 B |
505 - 8866525 REV B |
| ELECTRICAL-BERTHING |
19-DDG 54-30 B |
331 - 8866526 REV B |
| ELECTRICAL-SANITARY |
19-DDG 54-32 B |
331 - 8866527 REV B |
| VENTILATION-MFG DET |
19-DDG 54-52 B |
512 - 8866528 REV B |
|
| PROJECT NUMBERS(s) AND COMPARTMENTS |
BENL-S4383
2-78-01-L (75)
PT 1 (75)
HENL-S4385
2-97-01-L (14)
2-102-1-A (1)
PT 2 (15)
|
|
| MILESTONES |
SCHEDULED |
ACTUAL |
EVENTS |
| 02/08/2024 |
09/11/2019 |
09/11/2019
|
START SURVEY |
| 03/08/2024 |
09/26/2019 |
09/26/2019
|
COMPLETE SURVEY |
| 04/09/2024 |
10/25/2019 |
10/25/2019
|
SEND SURVEY REPORT TO PM |
| 02/27/2024 |
06/16/2024 |
06/17/2024
|
TC ISSUE ADVANCE PLANNING NOTICE TO SHIP |
| 03/28/2024 |
03/28/2024 |
Pending
|
SHIP RESPOND TO ADVANCE PLANNING NOTICE |
| 10/11/2024 |
09/30/2024 |
10/04/2024
|
SO SUBMIT DRAWINGS TO PM & PY |
| 10/11/2024 |
09/30/2024 |
10/07/2024
|
SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM |
| 06/11/2025 |
06/11/2025 |
Pending
|
PROJECT MATERIAL PROCUREMENT FUNDED |
| 09/08/2025 |
09/08/2025 |
Pending
|
PROJECT INSTALLATION FUNDED |
| 12/08/2025 |
12/08/2025 |
12/08/2025
|
START AVAILABILITY |
| 12/08/2025 |
12/08/2025 |
12/08/2025
|
START PROJECT |
| 09/29/2026 |
09/29/2026 |
Pending
|
COMPLETE PROJECT |
| 09/29/2026 |
09/29/2026 |
Pending
|
COMPLETE AVAILABILITY |
| Project Record Last Updated: 02/02/2026 |
|