Ship Project Status Report
(Blue Book)
Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM
S H I P H A B I T A B I L I T Y P R O J E C T D A T A
| JOHN PAUL JONES (DDG 53) |
21313-273
ACTIVE PROJECT
|
CLASS: DDG 51 (Flight I Variant) |
HOMEPORT: EVERETT |
PLANNING YARD: BATH |
|
| POC: Stephen Ferderer, CNSP N43 |
PHONE: 619-437-2757 |
|
| ENGINEERING WORK SCOPE |
| SURVEY AVAILABILITY: |
FY 23 DSRA3 |
| SURVEY DATES: |
10/31/2022 - 05/17/2024 |
| SURVEY LOCATION: |
EVER |
| DESIGN AGENT: |
DELPHINUS |
|
| INSTALLATION WORK SCOPE |
| INSTALL AVAILABILITY: |
FY 27 ISRA6-1
(149 days) |
| INSTALL DATES: |
06/21/2027 - 11/17/2027
|
| INSTALL LOCATION: |
EVER |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
3 / 207 |
3 / 18 |
0 / 0 |
16 / 39 |
22 / 264 |
| SANITARY SPACE / FIXTURES: |
10 / 39 |
5 / 17 |
0 / 0 |
8 / 26 |
23 / 82 |
|
| ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
| LIVING SPACES / BERTHS: |
0 / 0 |
0 / 0 |
0 / 0 |
0 / 0 |
0 / 0 |
| SANITARY SPACE / FIXTURES: |
2 / 10 |
0 / 0 |
0 / 0 |
0 / 0 |
2 / 10 |
|
| OTHER PROJECT: |
|
| PROJECT NO(S): |
BCPO-E9404, BENL-E9401, BOFF-E9405, HCPO-E9406, HENL-E9408, HOFF-E9407, |
| REMARKS: |
|
|
| OTHER PROJ: |
|
| REMARKS: |
CREW BERTHING #2 DEFERRED TO FY 30. |
|
| HABITABILITY DRAWING NUMBERS |
| DISCIPLINE |
HAB DRAWING NUMBER |
NAVSEA DRAWING NUMBER |
| ARRANGEMENT-SANITARY |
16-DDG 53-03 B |
644 - 8565822 REV B |
| VENTILATION-SANITARY |
16-DDG 53-12 B |
512 - 8565823 REV B |
| PIPE-SANITARY |
16-DDG 53-20 B |
505 - 8565824 REV B |
| ELECTRICAL-SANITARY |
16-DDG 53-32 B |
331 - 8565825 REV B |
| VENTILATION-MFG DET |
16-DDG 53-52 B |
512 - 8565826 REV B |
|
| PROJECT NUMBERS(s) AND COMPARTMENTS |
HENL-S9408
3-97-01-L (9)
3-102-1-A (1)
PT 2 (10)
|
|
| MILESTONES |
SCHEDULED |
ACTUAL |
EVENTS |
| 08/21/2025 |
03/21/2023 |
03/21/2023
|
START SURVEY |
| 09/19/2025 |
04/07/2023 |
04/07/2023
|
COMPLETE SURVEY |
| 10/21/2025 |
05/05/2023 |
05/04/2023
|
SEND SURVEY REPORT TO PM |
| 09/09/2025 |
07/07/2025 |
07/08/2025
|
TC ISSUE ADVANCE PLANNING NOTICE TO SHIP |
| 10/09/2025 |
07/28/2025 |
07/09/2025
|
SHIP RESPOND TO ADVANCE PLANNING NOTICE |
| 04/27/2026 |
04/27/2026 |
04/14/2026
|
SO SUBMIT DRAWINGS TO PM & PY |
| 04/27/2026 |
04/27/2026 |
04/14/2026
|
SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM |
| 12/23/2026 |
12/23/2026 |
Pending
|
PROJECT MATERIAL PROCUREMENT FUNDED |
| 03/22/2027 |
03/22/2027 |
Pending
|
PROJECT INSTALLATION FUNDED |
| 06/21/2027 |
06/21/2027 |
Pending
|
START AVAILABILITY |
| 06/21/2027 |
06/21/2027 |
Pending
|
START PROJECT |
| 11/17/2027 |
11/17/2027 |
Pending
|
COMPLETE PROJECT |
| 11/17/2027 |
11/17/2027 |
Pending
|
COMPLETE AVAILABILITY |
| Project Record Last Updated: 05/12/2026 |
|