Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM

Select by Ship Name: 

Select by Ship Hull: 

 

AMERICA (LHA 6)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
  FY 26 DSRA1   11/20/2025 - 10/09/2027 7 / 669 (b)   19 / 139 (f) 06/03/2022 Active
FY 30 SRA2-1   01/07/2030 - 02/11/2031 5 / 415 (b)   12 / 99 (f) 06/04/2026 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
AMERICA (LHA 6) 20103-261
ACTIVE PROJECT
CLASS: LHA 6
(FLIGHT 0)
HOMEPORT: SDGO PLANNING YARD: NNSY
POC: Stephen Ferderer, CNSP N43 PHONE: 619-437-2757
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 22 SRA1-2
SURVEY DATES: 04/04/2022 - 07/18/2022
SURVEY LOCATION: SASBO
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 26 DSRA1     (688 days)
INSTALL DATES: 11/20/2025 - 10/09/2027
INSTALL LOCATION: TBDWC
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 7 / 669 0 / 0 0 / 0 0 / 0 7 / 669
SANITARY SPACE / FIXTURES: 19 / 139 0 / 0 0 / 0 0 / 0 19 / 139
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 7 / 669 0 / 0 0 / 0 0 / 0 7 / 669
SANITARY SPACE / FIXTURES: 19 / 139 0 / 0 0 / 0 0 / 0 19 / 139
OTHER PROJECT:
PROJECT NO(S): BENL-E2382, HENL-E2383
REMARKS:
OTHER PROJ:
REMARKS:
HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-BERTHING 22-LHA 6-01  - 640 - 8866698  REV -
ARRANGEMENT-SANITARY 22-LHA 6-03  - 644 - 8866699  REV -
VENTILATION-BERTHING 22-LHA 6-10  - 512 - 8866700  REV -
VENTILATION-SANITARY 22-LHA 6-12  - 512 - 8866701  REV -
PIPE-FLUSHING WATER 22-LHA 6-26  - 521 - 8866703  REV -
PIPE-PLUMBING DRAIN 22-LHA 6-27  - 528 - 8866704  REV -
PIPE - POTABLE 22-LHA 6-28  - 533 - 8866705  REV -
ELECTRICAL-BERTHING 22-LHA 6-30  - 331 - 8937719  REV -
ELECTRICAL-SANITARY 22-LHA 6-32  - 331 - 8937720  REV -
ELECTRICAL-POWER SYSTEM 22-LHA 6-39  - 321 - 8937721  REV -
VENTILATION-MFG DET 22-LHA 6-52  - 512 - 8937722  REV -
PROJECT NUMBERS(s) AND COMPARTMENTS
BENL-S2382
1-25-0-L (93)
1-26-1-L (42)
1-26-2-L (51)
1-33-0-L (108)
2-33-0-L (243)
3-25-0-L (132)
3-26-1-L (0)
 PT 7 (669)
HENL-S2383
1-31-0-L (9)
1-31-1-A (1)
1-31.5-0-L (8)
1-31.5-1-L (9)
1-31.5-2-L (11)
1-31.5-3-L (7)
1-32.5-3-L (2)
1-32.5-4-A (1)
1-38.5-0-L (15)
1-40-1-L (5)
1-40.5-1-A (1)
2-39-0-L (18)
2-39.5-0-L (16)
2-39.5-1-L (10)
2-39.5-2-A (1)
3-31-0-L (10)
3-31-2-L (9)
3-32-0-L (5)
3-33-3-A (1)
 PT 19 (139)
MILESTONES SCHEDULED ACTUAL EVENTS
01/19/2024 06/03/2022 06/03/2022 START SURVEY
02/20/2024 06/24/2022 06/24/2022 COMPLETE SURVEY
03/22/2024 07/24/2022 07/19/2022 SEND SURVEY REPORT TO PM
02/09/2024 06/14/2024 06/17/2024 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
03/08/2024 03/08/2024 Pending SHIP RESPOND TO ADVANCE PLANNING NOTICE
09/26/2024 09/26/2024 11/25/2024 SO SUBMIT DRAWINGS TO PM & PY
09/26/2024 09/26/2024 11/26/2024 SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
05/23/2025 05/23/2025 Pending PROJECT MATERIAL PROCUREMENT FUNDED
08/21/2025 08/21/2025 Pending PROJECT INSTALLATION FUNDED
11/20/2025 11/20/2025 11/20/2025 START AVAILABILITY
11/20/2025 11/20/2025 11/20/2025 START PROJECT
10/09/2027 10/09/2027 Pending COMPLETE PROJECT
10/09/2027 10/09/2027 Pending COMPLETE AVAILABILITY
Project Record Last Updated: 11/24/2025