Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Friday, September 11, 2026 at 11:22 AM

Select by Ship Name: 

Select by Ship Hull: 

 

JOHN FINN (DDG 113)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
  FY 27 DSRA1   07/20/2027 - 06/12/2028 6 / 60 (b)   8 / 29 (f) 06/12/2024 Active
FY 30 SRA2-1   09/03/2030 - 04/14/2031 2 / 135 (b)   4 / 26 (f) 07/20/2027 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
JOHN FINN (DDG 113) 20010-274
ACTIVE PROJECT
CLASS: DDG 51
(Flight IIA Variant)
HOMEPORT: YOKO PLANNING YARD: BATH
POC: Stephen Ferderer, CNSP N43 PHONE: 619-437-2757
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 24 SRA1-2
SURVEY DATES: 04/08/2024 - 11/18/2024
SURVEY LOCATION: SRFYOKO
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 27 DSRA1     (328 days)
INSTALL DATES: 07/20/2027 - 06/12/2028
INSTALL LOCATION: SRFYOKO
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 11 / 292 4 / 27 0 / 0 0 / 0 15 / 319
SANITARY SPACE / FIXTURES: 17 / 67 5 / 17 0 / 0 0 / 0 22 / 84
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 6 / 60 0 / 0 0 / 0 0 / 0 6 / 60
SANITARY SPACE / FIXTURES: 8 / 29 0 / 0 0 / 0 0 / 0 8 / 29
OTHER PROJECT:
PROJECT NO(S): BCPO-E4458, BENL-E4459, HCPO-E4460, HENL-E4461
REMARKS: ALT SA DDG 0051 87378 D 00 INCREASE CREW BERTHING SCHEDULED IN NDE FY 24. PE REPORTS, 23 BUNKS ADDED. 12/8/25 EEN
OTHER PROJ:
REMARKS: CREW BERTHING #3 (2-310-2-L) DROPPED AS REQUESTED.
CREW COMPLEXES #4 AND #6 ADDED AS REQUESTED.
2-300-3-L. COMPLETED DURING FY 25 CMAV BY OTHERS. REMOVED FROM THIS WORK SCOPE.
HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-BERTHING 24-DDG 113-01  A 640 - 8937661  REV A
ARRANGEMENT-SANITARY 24-DDG 113-03  A 644 - 8937662  REV A
VENTILATION-BERTHING 24-DDG 113-10  A 512 - 8937663  REV A
VENTILATION-SANITARY 24-DDG 113-12  A 512 - 8937664  REV A
PIPE-SANITARY 24-DDG 113-20  A 505 - 8937665  REV A
ELECTRICAL-BERTHING 24-DDG 113-30  A 331 - 8937666  REV A
ELECTRICAL-SANITARY 24-DDG 113-32  A 331 - 8937667  REV A
VENTILATION-MFG DET 24-DDG 113-52  A 512 - 8937668  REV A
PROJECT NUMBERS(s) AND COMPARTMENTS
BENL-S4459
2-300-1-L (9)
2-314-3-L (0)
2-326-1-L (6)
3-300-1-L (27)
3-326-1-T (0)
3-338-3-L (18)
 PT 6 (60)
HENL-S4461
2-314-2-L (11)
2-314-4-A (1)
2-330-2-L (2)
2-334-0-L (2)
3-325-1-L (6)
3-335-1-A (1)
3-338-5-A (1)
3-338-7-L (5)
 PT 8 (29)
MILESTONES SCHEDULED ACTUAL EVENTS
09/19/2025 06/12/2024 06/12/2024 START SURVEY
10/17/2025 06/23/2024 06/23/2024 COMPLETE SURVEY
11/19/2025 07/22/2024 08/05/2024 SEND SURVEY REPORT TO PM
10/08/2025 08/26/2025 08/25/2025 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
11/07/2025 09/25/2025 08/27/2025 SHIP RESPOND TO ADVANCE PLANNING NOTICE
05/26/2026 04/13/2026 04/13/2026 SO SUBMIT DRAWINGS TO PM & PY
05/26/2026 04/13/2026 04/13/2026 SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
01/21/2027 01/21/2027 Pending PROJECT MATERIAL PROCUREMENT FUNDED
04/20/2027 04/20/2027 Pending PROJECT INSTALLATION FUNDED
07/20/2027 07/20/2027 Pending START AVAILABILITY
07/20/2027 07/20/2027 Pending START PROJECT
06/12/2028 06/12/2028 Pending COMPLETE PROJECT
06/12/2028 06/12/2028 Pending COMPLETE AVAILABILITY
Project Record Last Updated: 07/22/2026